Hedgeley Malvern East – March 2018 Project News

Little Projects


CONSTRUCTION UPDATE

Hedgeley Malvern East is beginning to take shape with the slab for the atrium garden level now complete.

The curves of the building are forming, and will soon be visible from Waverley Road. The team at Hutchinsons are working to finish the ground floor slab by the end of March, along with the first pours of the first floor.

This week, services installation will commence in the basement and precast walls continue to be erected across the ground floor. Earlier this month, our delivery team inspected all kitchen and bathroom joinery at the joiner’s factory to ensure all materials met the project team’s high standards. The inspection was successful, and the joinery will soon commence production.

Completion of Hedgeley is anticipated for late-2018.

 

LIMITED RESIDENCES AVAILABLE

A limited number of luxury residences are available at Hedgeley Malvern East. If you have any family or friends interested in buying at Hedgeley, please contact Greg Curtis on 0430 448 566.

 

ONGOING COMMUNICATION

We will continue to communicate with you regularly by email throughout the construction journey. If you would like to add an additional email address for a partner, family member or an additional email address for yourself, please email your apartment number and the additional email address to settlements@littleprojects.com.au.

Project News updates are also available to view on the Little Projects website under News.

 