A central place for our project updates to our purchasers. We take great pride in sharing news, updates and step-by-step guides with our customers throughout the entire process.
A central place for our project updates to our purchasers. We take great pride in sharing news, updates and step-by-step guides with our customers throughout the entire process.
Little Projects
July 17th, 2019
An important notice for purchasers of apartments on Levels 6 to 10 at Grace Victoria Quarter. Read more
Little Projects
June 10th, 2019
The project team gathered on site alongside purchasers, agents and the community to celebrate the project's most successful milestone to date. Read more
Little Projects
May 1st, 2019
Removal of the scaffold at Grace has commenced, with one-third of the building's facade now visible from Sale Street. Over the coming month, the scaffold will continue to be removed, revealing the building's grand architectural form. Read more
Little Projects
March 22nd, 2019
2019 is off to a positive start at Signature Broadbeach. Read more
Little Projects
March 4th, 2019
2019 is off to a flying start at Grace Victoria Quarter with Macrennie continuing to work through internal fit-out of apartments on the upper levels. Read more
Little Projects
February 12th, 2019
We advise that settlement has been called for apartments on levels C, E, 1, 2 and 3 at Hedgeley Malvern East. Read more
Little Projects
December 19th, 2018
Welcome to the final Signature Broadbeach project update for 2018. We are pleased to be closing out the year with demolition of the existing building on site now complete. Read more
Little Projects
December 18th, 2018
The team has commenced kitchen installation on levels 1 and 2. In the coming weeks, Macrennie will work towards ensuring the entire building is water tight and installing all timber floors to level 1. Read more
Little Projects
December 12th, 2018
We advise that all apartments including those on levels 3 and 4 are now available for finance valuations. Read more
Little Projects
December 4th, 2018
Little Projects is disappointed to advise that the Plan of Subdivision will not be registered in time to allow for settlements to occur prior to Christmas. Read more
Little Projects
November 20th, 2018
Great progress has been made to the internals of apartments on ground to level 2 since our last update. Read more
Little Projects
November 9th, 2018
We are pleased to notify you that a letter has been sent to your solicitor/conveyancer advising that apartments on level C to level 2 are now available for finance valuations. Read more