Signature Broadbeach Construction Update - August 2021

Project Updates | 13 Aug 2021

Signature Broadbeach Construction Update - August 2021

The Level 19 concrete slab is now complete with the core and jumpform currently at Levels 22 and 23 respectively. The tower crane is at Level 24.

Facade glazing is progressing which is now complete to Level 11.

We are moving along as scheduled with an average 160 workers on site every day with lift installation underway on lower levels, internal partitions complete up to level 8 and tiling underway on levels 5 & 6.

Signature remains on schedule for completion in the first half of 2022.

At this stage, COVID-19 has not meaningfully delayed our program, we will continue to keep our you updated should this change.