Signature Broadbeach – September 2019 Project News

Project Updates | 24 Sep 2019

Signature Broadbeach – September 2019 Project News

As we move into spring, construction activity continues on site at Signature with the builders busy installing pile foundations.
View the on site construction progress from May - August 2019.

CONSTRUCTION UPDATE

As we move into spring, construction activity continues on site at Signature with the builders busy installing pile foundations. These are deep concrete columns within the ground which provide the base for Signature’s structure. 37 pile foundations are now complete, constructed to depths of 50 metres below ground.

Construction of the basement perimeter ”diaphragm wall” will commence this week, and the basement perimeter guide wall installation is complete.

Specialised ground anchors, which will be installed to the diaphragm wall during basement excavation, have been ordered and are on their way to Broadbeach from Germany.

Completion at Signature is anticipated for the first half of 2022.

FEATURE APARTMENT

An unrivalled investment opportunity – achieve a return of over 6%*

APARTMENT 2103
2 bedroom | 2 bathroom | 1 car
$832,500
Click to view floor plan
To enquire, contact Natasha Pezet on 07 4408 0999 or npezet@kmsm.com.au.

Click here to discover more about Signature Broadbeach.